Recently, all villas reached their highest structural point, marking the successful completion of the main structural works.
To celebrate this achievement, we proudly held the traditional topping out ceremony together with the project team and partners.
Construction activities are progressing steadily across the site.
Roofing works have been completed and internal structural works are finished.
Installation of exterior windows and garage gates is currently ongoing, while facade works are being executed in parallel.
Plastering works are scheduled to start shortly.
The project is progressing on schedule, and each week brings us closer to the final stages.
What sets Wiedeńska Residence apart is its exceptional care for nature.
As part of the development, over 500 trees have been preserved, creating a natural green canopy that ensures privacy and tranquility.